Mike Kushy. Repeat of yesterday, several hours surface work moving spoil from heap 1 to the track. MK.
TempleTwin
Tuesday, 18 August 2026
Monday, 17 August 2026
Monday 17th August 2026
Mike Kushy. Several hours surface work moving spoil from heap 1 to the track. MK.
Saturday, 15 August 2026
Saturday 15th August 2026
Mike Kushy, Alessio Sancetta and Lee Venning arrived on site at 10am. The weather was sunny and warm. We set the extractor up, then AS headed down shaft to fill buckets with MK on the winch and LV emptying. After 37 x buckets had been winched to the surface we stopped for lunch.
After lunch LV went down shaft with the large breaker. Once a further 20 x loads had been winched topside LV returned to the surface, with AS replacing him down the shaft to have a go on the breaker. Another 3 loads were winched up and then MK joined AS down shaft to make a start drilling. Unfortunately after only half a hole LV’s drill packed up (I’m going to repair it today), so we abandoned the set up and called it a day.
Depth measured at 16.15m. We all left site at 4.30pm. 6½ hours.
Total Buckets Removed x 60. Lee.
|
| Today's load count. Photo LV. |
Sunday, 9 August 2026
Sunday 9th August 2026
Sunday, 2 August 2026
Sunday 2nd August 2026
John Cooper, Trevor Hughes, Mike Kousiounis, Adrian Miles and Henry Miles. Hot again, 26°C on surface. John and Kushy set up then Kushy went down to start drilling. When the others arrived the surface team shifted spoil from the South side to a safer position whilst Kushy completed drilling. Four 32mm holes each charged with 1 stick. Extractor fan used again at end clearing fumes. 3 hours.
Saturday, 1 August 2026
Saturday 1st August 2026
Mike Kushy and Lee Venning arrived on site at 10.45am. The weather was sunny and warm. We set the extractor up and then LV headed down to fill buckets while MK was on winch duty. After about 15 x buckets had been winched to the surface MK was joined Mikey Waterworth (MW). Once 30 x loads had been winched topside LV returned to the surface, with MW replacing him down the shaft armed with the small breaker. MW stayed underground until we reached a total of 48 buckets.
We stopped for lunch as it was 2pm already and afterwards MK went down shaft to continue work with the breaker, after a further 10 loads we called it a day.
We all left site at 3:15pm, 4 ½ hours, Lee.
Total Buckets Removed x 58
|
| Base at end of session. Photo MK. |
|
| Loads hauled up today. Photo LV. |
Monday, 27 July 2026
Monday 27th July 2026
John Cooper, Mike Kousiounis and Lee Venning, with a visit from David Morrison. John arrived about 16.45 and started setting up. Mike arrived about 17.00 and arranged the extractor fan and then descended to start drilling. Lee arrived about 17.15 and descended to assist Mike. Four 32mm holes 600mm deep drilled and charged. All equipment removed and spoil created. Extractor fan run again to remove fumes. 1½ hours. John.