Sunday, 29 November 2026

Sunday 29th November 2026

Trevor Hughes, Mike Kushy and Kate Lawrence. We met up for 1330. MK went down the hole with TH and KL on surface duties. 3x20l containers were sent down to MK. The puddle was around 10inch deep, 2m long by 1m wide and stinking. To begin bailing was easy, pushing the containers into the puddle and letting nature do it's work, the last several loads needed bailing with a jug. Half filled containers sent up, 16 loads, so roughly 160L bailed (took 30 minutes to clear). 16 buckets of spoil cleared afterwards and the narrow rift revealed again with lots of mud pulled out of it, hopefully giving better drainage. Didn't check the time but believe we finished around 1530. We went to check out a depression near The Ploughboy Inn afterwards, neither of us had ever noticed it before even though it's right next to the road and it's big. Mike.

End of session. Photo MK.

Sunday, 25 October 2026

Mike Kousiounis (Kushy) and Lee Venning. 10.30. Dig is flooded. At least 1m underwater. Mike.

Trevor Hughes. I went there at about 1300 and got caught in a cloud burst, it’s even wetter now. Trevor.

Pool at bottom. Photo MK.

Sunday, 18 October 2026

Sunday 18th October 2026

John Cooper, Trevor Hughes, Mike Kousiounis (Kushy) and Lee Venning. Trevor to the bottom with plug and feathers to break up the large rocks into ones suitable for hauling out, 22 loads. Once completed he came out and Kushy went in. He filled more loads until we reached a total of 42 removed. Still plenty more to come out. 2 hours. John.

Trevor drilling for p/f. Photo MK.

Spoil remaining at end of session. Photo MK.

Sunday, 11 October 2026

Sunday 11th October 2026

John Cooper, Trevor Hughes and Mike Kousiounis (Kushy). Kushy loading, John hauling and Trevor emptying. Stopped at 63 loads as John’s call-out time was approaching. A couple of large boulders need breaking up. 2 hours. John.

Boulders to break up next time. Photo MK.

Today's count. Photo JC.

Tuesday, 29 September 2026

Tuesday 29th September 2026

Mike Kushy, solo. Arrived at 1300, set up breaker and started at the bottom removing the slope. The breaker was then raised and all the loose blocks near the RSJ removed. Estimate about 50 buckets worth to clear at least. Left at 1700. Mike.

Spoil for clearing. Photo MK.

Crystals. Photo MK.

Sunday, 27 September 2026

Sunday 27th September 2026

Trevor Hughes, Xiao Jin, Mike Kushy and Lee Venning. XJ, MK and LV to begin with, we met around 10am. Extractor ran initially but still fumey below, so we rigged up the other fan to a 10m pipe. This was used as the extractor (exhaust) half way down the shaft with the other longer fan pumping air to the very bottom, this created a really good draught cycle and the air cleared quickly. MK down the bottom with LV and XJ clearing, 42 cleared then we stopped for lunch. XJ then went down the hole and we cleared 62 in total. TH arrived near the end and so did the heavy rain, which put a stop to things. A dozen buckets of loose at the bottom to clear still and breaker work to do. Up by the RSJ you can see that our recent bangs have been loosening up some big rock, which needs removing next session and this will also allow us to make space for the next ladders to go in. Left around 1430. Mike.

Loads out today. Photo LV.

Spoil removal. Photo MK.

Sunday, 20 September 2026

Sunday 20th September 2026

John Cooper, Xiao Jin, Mike Kousiounis (Kushy) and Lee Venning. Warm and dry today, 20°C. Kushy down to start with loading buckets. After 45 sent up he came out and John went down with breaker. Stopped at 62 loads hauled out for the day. Lee then down using electron ladder as the extendable ladder had been left insecurely perched! Drilled 5 holes then replaced by Mike to do the final one. Depth measured. Extendable ladder removed and charge set up and fired once electron ladder removed. There is now no in situ ladder to the bottom! 5 hours. John.

Today's loads hauled out. Photo LV.