Mike  Kushy. Arrived at 10.30 am. Went to WRH and collected some wall building rock, I did 3 trips in total. Moved rock closer to site and swept everything down. Moved the pallet and posts out of the way and lowered a short piece of steel I beam down (roughly 1&1/2 ft). Had to chisel some out of the west wall, it got very solid so I just hammered back the steel as far as it would go. Pins drilled and fitted each end. 3 mixes used to build off the steel to the one above. 2 more mixes used to build up the South wall. Several buckets of spoil removed from the floor and tipped behind the south wall. A nice hole at the bottom, we need a bigger ladder. 8 hours. Mike.