Mike Kushy and John Cooper. MK to start with, arrived at 10am. Did 2 runs of building rock from WRH. Then 2 mixes were used to build up the south wall some more. This was then back filled with small stone from the spoil heap. I then did 2 more runs for rock. JC showed up with a load of rocks at 14.30 as I was handling the rocks from the car. The pair moved all the rock to the dig and JC started on another big mix. Meanwhile MK was removing wood props and preparing to bring the wall round. We also decided to build up under the arch so we can set the props higher to finish the walling. 6 hours. Mike.
 |