Friday, 23 May 2025

Friday 23rd May 2025

Mike Kushy. 3 mixes made and used to finish the retaining wall to the south (soil can go behind this now ready for bushes to be planted). Also started building the ladder pit entrance wall to the west. Once this is built the scaffold legs for the winch can be brought in closer and the angle for winching made steeper. 4 hours. Mike.

Ladder pit in construction. Photo MK.

Retaining wall to the south. Photo MK.