Mike Kushy, Alessio Sancetta and Lee Venning arrived on site at 10am. The weather was sunny and warm. We set the extractor up, then AS headed down shaft to fill buckets with MK on the winch and LV emptying. After 37 x buckets had been winched to the surface we stopped for lunch.
After lunch LV went down shaft with the large breaker. Once a further 20 x loads had been winched topside LV returned to the surface, with AS replacing him down the shaft to have a go on the breaker. Another 3 loads were winched up and then MK joined AS down shaft to make a start drilling. Unfortunately after only half a hole LV’s drill packed up (I’m going to repair it today), so we abandoned the set up and called it a day.
Depth measured at 16.15m. We all left site at 4.30pm. 6½ hours.
Total Buckets Removed x 60. Lee.
|